ecr: 28
This data as json
| rowid | customer_name | customer_site | address_line_1 | address_line_2 | city | county | postcode | gsp | bsp | primary | voltage | energy_source | connection_status | connected_export | accepted_export | accepted_import | date_accepted | date_published | source | lat | lon | project_id | location_gsp | location_bsp | location_primary | substation_id_gsp | substation_id_bsp | substation_id_primary | retain_edits |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 28 | mercia power response (graphite way) ltd | site 3 | graphite way | graphite way | glossop | derbyshire | sk13 1qh | stalybridge gsp | hyde | hattersley | 11.0 | fossil - gas | connected | 6.0 | 0.0 | 0.0 | 15/01/2025 | enw | 53.46629202055618 | -1.9787070916472802 | enw_project_207 | stalybridge | hyde | hattersley | enw_gsp_stalybridge | enw_bsp_hyde | enw_primary_hattersley | 0 |